Planned Value formula (PV)

Planned Value (PV)

As per the PMBOK Guide, “Planned Value (PV) is the authorised budget assigned to work to be accomplished for an activity or WBS component.”

The project’s total planned value is known as your budget at completion or BAC and is calculated by summing up the PV for each activity, operation, or task, within your project.

Planned value formula

To calculate the planned value, multiply the percentage of completed work (planned) by the project’s budget (BAC).

Planned Value is calculated by multiplying the (planned) work % complete by our projects budget or BAC

PV = (planned) % complete x BAC

Using this example, let’s calculate our planned value.

1. After 1 month

As you can see in the table above, our project is scheduled for four months. So, after one month, we should (should!) have completed 25% of the work.

E.g.

  1. Project duration: 4 months
  2. BAC: $40,000
  3. Elapsed time: 1 month
  4. (planned) % complete: 25%

PV = % complete (planned) x BAC

PV = 25% x $40,000

PV = $10,000

2. After 2 months

So, based on our four-month schedule, by the second month, we should have completed 50% of the work.

E.g.

  1. Project duration: 4 months
  2. BAC: $40,000
  3. Elapsed time: 2 months
  4. (planned) % complete: 50%

PV = (planned) % complete x BAC

PV = 50% x $40,000

PV = $20,000