DYNO NOBEL
MORANBAH
Ammonia Plant Shutdown
Year: 2024
Total Labour: 6,200hrs / 14 Days
Total Schedule Activities: 2,400
Cost: $2.5m

INCITEC PIVOT
PHOSPHATE HILL
Three Shutdown events,
15-week cycle
Year: 2023
Labour per event: 8,000hrs / 5 Days
Schedule Activities per event: 3,000
Cost per event: $1.5m

MILLMERRAN POWER
MILLMERRAN
Power Station Shutdown
Year: 2023
Total Labour: 86,000hrs / 28 Days
Total Schedule Activities: 8,023
Cost: $15m

ARROW ENERGY
SURAT BASIN
David Inlet Processing Facility Construction
Year: 2022
Total Labour: 15,020hrs / 10 Months
Total Schedule Activities: 1,210
Cost: $18.2m

INCITEC PIVOT
PHOSPHATE HILL
Ammonia Plant Turnaround
Year: 2022
Total Labour: 93,350hrs / 51 Days
Total Schedule Activities: 18,254
Cost: $100m

INCITEC PIVOT
PHOSPHATE HILL
Three Shutdown events,
15-week cycle
Year: 2022
Labour per event: 8,000hrs / 5 Days
Schedule Activities per event: 3,000
Cost per event: $1.5m

ARROW ENERGY
SURAT BASIN
David Inlet Processing Facility Construction
Year: 2021
Total Labour: 15,020hrs / 10 Months
Total Schedule Activities: 1,210
Cost: $18.2m

INCITEC PIVOT
PHOSPHATE HILL
Three Shutdown events,
15-week cycle
Year: 2021
Labour per event: 8,000hrs / 5 Days
Schedule Activities per event: 3,000
Cost per event: $1.5m

RIO TINTO
YARWUN
Alumina Refinery Shutdown
Year: 2021
Total Labour: 144,000hrs / 95 Days
Cost: $21m